Sequence and schedule project activities and resources
Sequence and schedule project activities and resources assignment
ROHINI COLLEGE OF ENGINEERING AND TECHNOLOGY
Sequencing and Scheduling Activities
Ø Project and its activities must be clearly defined to achieve the target. An activity plan will contain the following factors:
A project is basically, composed of number of interrelated activities.
The initiation of a project happens only if atleast one activity is ready to start.
An activity is clearly defined with its start and end point that produce gooddeliverables.
Activity requiring resources must be analyzed well in advance and made available during the execution.
Some activities would depend on other activities for them to complete.
A project can attain its completion only when all activities have beencompleted.
Approaches to Identify Activities
Ø The various approaches used in identifying activities are:
Activity-based approach Product-based approach
Hybrid approach
Activity-based approach
Ø In the activity-based approach, all the activities are listed and created for the project.
Ø This is achieved by a brainstorming session where the entire project team analysis the various activities needed a0t different stages with the help of similar projects.
Ø This approach usually generates the list of activities using a work breakdown structure (WBS).
Ø WBS helps in identifying the lowest level of effort i.e. the task required to complete a project by breaking down into lower sets of tasks.ØTask defined at lower level includes everything that is required to complete the task at the
higher level.
ØThe work breakdown structure provides an in-depth knowledge about the lowest level of activity that has to be completed.
ØWBS is a refined structure that clearly defines the milestones that has to be achieved in accomplishing a specific task.
ØThe ordering of sequence of activities can also be done in this approach by defining those activities that have to be completed for others to start.
ØIn a purely activity-based approach, activities are identified and defined in fivelevels:
Level 1 : Project–goals, objectives defined
Level 2: Deliverables–software, manuals, training Level 3 : Components–work items, modules, tests
Level 4 : Work-packages–major work items, related tasks
Level 5 : Tasks–responsibility of an individual in accomplishing it Product-based approach
Ø The product-based approach produces a product breakdown structure along with a product flow diagram.
Ø The approach accepts the products as inputs which is transformed into an ordered list of activities.
Ø Product Flow Diagram do not leave out any activity from its ordered list and adopts a methodology which clearly specifies what are the products required and what are the activities required to produce the product.e
Ø Using Structured Systems Analysis and Design Method (SSADM), a generic activity network can be derived for a project-specific product breakdown structure.
Ø The development of a PFD indicates the sequence of activities of the activitynetwork.
Hybrid approach
Ø WBS deals with list of final deliverables whereas PBS deals in producing the products using the product flow diagram.
Ø Hybrid approach combines both the activity-based and product-based approach to structure both activities and products.
Ø Structuring of product-based or activity-based approach depend on the nature of the project type.Figure – Hybrid Approach combining Activities and Products
Sequencing and scheduling activities
Ø Scheduling is required for every activity that is planned along with the resources and can be represented using a bar chart.
Ø The chart describes the nature of the development process and the resources available for completing the specified activities
| Weeks
Person |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Requirements | ||||||||||||
| Design Module1 | ||||||||||||
| Design Module2 | ||||||||||||
| Design Module 3 | ||||||||||||
| Code Module1 | ||||||||||||
| Code Module2 | ||||||||||||
| Code Module 3 | ||||||||||||
| Integration | ||||||||||||
| System Acceptance | ||||||||||||
Figure – Bar chart representing Scheduling
Ø The chart defines two factors: sequencing of tasks and the schedule of the task. Scheduling includes the staff availability and the activities allocated to them.
Ø Combining sequencing – scheduling approach is suitable only for smaller projects and needs to be separated for complex projects as individual process.
Ø In case of larger projects, the logical relationship between the activities are grouped together and then scheduled for resources.
